    A project can be done in 35 days by 12 people. However, after 25 days the project paused for 5 days. How many people need to be added?

    I guess it's 12. Am I right?

  2. # ADS
    Circuit advertisement
    Join Date
    Always
    Posts
    Many
     

  3. Pessimist Singularitarian
    MHB Coder
    MHB Math Helper
    MHB Ambassador
    MarkFL's Avatar
    Status
    Offline
    Join Date
    Feb 2012
    Location
    St. Augustine, FL.
    Posts
    13,311
    Thanks
    34,279 times
    Thanked
    31,687 times
    Thank/Post
    2.381
    Trophies
    25 Highscores
    Awards
    MHB Chat Room Award (2017)  

MHB Calculus Award (2017)  

MHB Pre-University Math Award (2017)  

MHB Statistics Award (2016)  

MHB Calculus Award (2016)
    #2
    After 25 days, 2/7 of the job is left to be done. 1 person can do 2/7 of the job in 120 days, so it would take 120/5 = 24 people to do 2/7 of the job in 5 days, so yes, 12 people need to be added.

  4. MHB Craftsman
    Monoxdifly's Avatar
    Status
    Offline
    Join Date
    Aug 2015
    Posts
    261
    Thanks
    34 times
    Thanked
    86 times
    #3 Thread Author
    How did you get that 120 days?

  5. Pessimist Singularitarian
    MHB Coder
    MHB Math Helper
    MHB Ambassador
    MarkFL's Avatar
    Status
    Offline
    Join Date
    Feb 2012
    Location
    St. Augustine, FL.
    Posts
    13,311
    Thanks
    34,279 times
    Thanked
    31,687 times
    Thank/Post
    2.381
    Trophies
    25 Highscores
    Awards
    MHB Chat Room Award (2017)  

MHB Calculus Award (2017)  

MHB Pre-University Math Award (2017)  

MHB Statistics Award (2016)  

MHB Calculus Award (2016)
    #4
    Quote Originally Posted by Monoxdifly View Post
    How did you get that 120 days?
    1 person can do the entire job in 12*35 = 420 days, so it would take 1 person (2/7)(420) = 120 days to do 2/7 of the job.

  6. MHB Craftsman
    Monoxdifly's Avatar
    Status
    Offline
    Join Date
    Aug 2015
    Posts
    261
    Thanks
    34 times
    Thanked
    86 times
    #5 Thread Author
    Sorry, I did a typo in the first post. It should be like this:
    Quote Originally Posted by Monoxdifly View Post
    A project can be done in 35 days by 12 people. However, after 24 days the project paused for 5 days. How many people need to be added?

    I guess it's 12. Am I right?
    Being said, guess 12 isn't correct.

  7. MHB Master
    MHB Math Helper

    Status
    Offline
    Join Date
    Jan 2012
    Posts
    1,100
    Thanks
    318 times
    Thanked
    1,098 time
    #6
    So "after 24 days" rather than "after 25 days"? That's odd- it just makes the numbers messier. Do the same thing MarkFl did. 24/35 of the job has already been done. In order that the job still be completed in the full 35 days, we must complete the 1- 24/35= 11/35 of the job in the remaining 6 days. That means we must complete (11/35)/6= 11/210 job per day. Since the original 12 people could do the job in 35 days, each person works at 1/(35*12)= 1/420 "job per day". To do 11/210 job at a rate of 1/420 job per person, we must have (11/210)/(1/420)= (11/210)(420/1)= 22 people. We must add 22- 12= 10 new people.

  8. MHB Craftsman
    Monoxdifly's Avatar
    Status
    Offline
    Join Date
    Aug 2015
    Posts
    261
    Thanks
    34 times
    Thanked
    86 times
    #7 Thread Author
    So, basically the calculation is $ \displaystyle \frac{12\times(35-(24+5)+5)}{6}$?

  9. MHB Apprentice
    calculateboard's Avatar
    Status
    Offline
    Join Date
    May 2016
    Location
    SZagora
    Posts
    4
    Thanks
    0 times
    Thanked
    0 times
    #8
    25/35 of the project is completed
    12 people can do 1/35 a day
    you need to do 10/35 in 5 days
    12 people can do 5/35 in 5 days
    so you need twice as more people

Similar Threads

  1. Ratio
    By wailingkoh in forum Pre-Algebra and Algebra
    Replies: 2
    Last Post: December 10th, 2015, 04:41
  2. Find the value of the ratio of m/n
    By anemone in forum Challenge Questions and Puzzles
    Replies: 3
    Last Post: May 30th, 2014, 23:16
  3. Ratio of coefficients
    By Pranav in forum Pre-Algebra and Algebra
    Replies: 8
    Last Post: March 27th, 2014, 15:44
  4. Ratio and proportion
    By kuheli in forum Pre-Algebra and Algebra
    Replies: 7
    Last Post: November 8th, 2013, 10:24
  5. Cross ratio
    By Impo in forum Topology and Advanced Geometry
    Replies: 1
    Last Post: June 27th, 2013, 17:02

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Math Help Boards