Homework Statement
If 15 workers can pave 18 driveways in 24 days, how many days would it take 40 workers to pave 22 driveways?
Homework Equations
Set of worker * driveways* days/Another set of workers * driveways
The Attempt at a Solution
15 * 18 *24/40 * 22 =54/11 wrong
Some body please guide. I don't know the method for solving such problems. I don't know the usage of two set of data.
Zulfi.[/B]